What is the difference between EERA and PFEER?

PFEER is the UK legal framework. EERA is a commonly used name for the technical assessment and evidence used to demonstrate the relevant emergency-response duties. The assessment is the work product; PFEER defines the legal obligations.
Continue Reading
The team should collectively understand process and major-accident hazards, fire and explosion effects, toxic-gas analysis, human factors and egress, offshore layout, TR/HVAC performance, marine or aviation evacuation, recovery and rescue, and the applicable regulatory regime.
Continue Reading
PFEER requires the assessment to be repeated as often as appropriate. Review it after relevant modifications, POB or occupancy changes, route or TR changes, equipment changes, drill findings, incidents, new hazard information and Safety Case reviews.
Continue Reading
The scenario set should be driven by the facility hazard assessment and can include jet and pool fires, explosions, blowouts, toxic or asphyxiant releases, non-process fires, structural damage, flooding or loss of stability, ship or aircraft impact, extreme weather, loss of utilities and combined events.
Continue Reading
No single speed is suitable for every route or person. Use validated values for level walkways, stairs, ladders and congested flow, adjusted for visibility, PPE, route condition and mobility. Include pre-movement and queueing, and calibrate the model against drills.
Continue Reading
HSE does not prescribe a universal sixty-minute duration. The duty holder must define and demonstrate a realistic survival time for the major-accident hazard profile and show that evacuation or escape can be completed within that time.
Continue Reading
There is no universal ten-minute requirement in current HSE guidance or NORSOK Z-013:2024. The criterion should be installation- and scenario-specific, based on route impairment, emergency actions, the muster strategy and the relevant performance standards.
Continue Reading
Not necessarily. A muster area is where people assemble and are accounted for. A TR is a protected location with a defined survival function. A muster area may be inside a TR, and alternative muster locations may be needed for scenarios that impair the main TR.
Continue Reading
The PFEER regulation 5 assessment is mandatory. UK law does not prescribe one report format or require the document to be titled “EERA”. The duty holder must be able to show a recorded, current and technically adequate assessment with measurable performance standards.
Continue Reading
EERA stands for Evacuation, Escape and Rescue Analysis. A complete offshore assessment also addresses recovery of evacuees and escapees, because PFEER treats recovery and rescue as essential parts of the protection chain.
Continue Reading